Resurfacing on Highways 1804 and 204 Set to Begin





For Immediate Release:  Tuesday, August 27, 2019 

Contact:  Dean VanDeWiele, 605-773-5294 

 

 

PIERRE, S.D. – The South Dakota Department of Transportation says work will begin Sept. 4, on an asphalt resurfacing project on highways 1804 and 204 near Pierre.

 

The project limits are from the junction of Highway 14 north on Highway 1804 to one mile north of the Hughes/Sully County line and across the dam on Highway 204.

 

The contractor will begin by milling one inch of the existing surface starting Wednesday, Sept. 4, followed by asphalt surfacing beginning on or about Sept. 12.

 

During all operations traffic will be carried through the work zones with the use of flaggers and/or a pilot car. Motorists can expect delays during these times and will need to plan accordingly.

 

The contractor expects to complete the project and restore traffic by Oct. 15, depending on weather, with an overall completion date of Nov. 1.

 

The contractor on this $4.8 million project is Duininck, Inc. of Prinsburg, Minnesota.

 

For more information, contact Dean VanDeWiele at 605-773-5294.

 

For complete road construction information, visit www.safetravelusa.com or dial 511.

 