Work begins on US 18 between US 81 and Olivet


Article Body

Department of Transportation

Yankton Area Office

1306 West 31st Street

Yankton, SD  57078-9662

PHONE:  605/668-2929    FAX:  605/668-2927

Web: www.SDDOT.com 

 

 

For Immediate Release:   April 23 , 2009

Contact: Greg Rothschadl, Yankton Area DOT, 605-661-8623 or Ron Peterson, DOT, 605-668-2929

 

Work  begins on US 18 between US 81 and Olivet 

 

YANKTON, S.D.  South Dakota Department of Transportation officials report that work began April 2, 2009, on cold milling asphalt concrete and asphalt concrete resurfacing on US 18 from US 81 to Olivet. 

 

During construction, travelers on US Highway 18 should be prepared to stop for flaggers and should expect a brief delay while waiting for the pilot car.  

 

Spencer Quarries, Inc. of Spencer, SD is the prime contractor on the project at a total cost of 2.2 million dollars. Work is expected to be completed by June 1, 2009.  

 

For more information, contact Greg Putnam, Yankton Area DOT, 605-661-2424 or Ron Peterson, Yankton Area DOT, 605-668-2929.

 

- 30 -