Traffic Switch Scheduled for Southbound Interstate 29 in Sioux Falls


Article Body

For Immediate Release:
Tuesday, July 8, 2025


Contact:
Harry Johnston, Sioux Falls Area Engineer, 605-367-5680

 

SIOUX FALLS, S.D. – On Thursday, July 10, 2025, a traffic switch is scheduled to take place on southbound Interstate 29 on the bridge over Skunk Creek in Sioux Falls. Traffic will be placed in the two easternmost lanes to allow for crews to complete work in the two westernmost lanes. 

 

This traffic configuration is anticipated to be in place until Friday, Aug. 15, 2025. Once work is complete, traffic will be restored to its traditional configuration.

 

The prime contractor for this $7.4 million project is General Excavating, LLC of Lincoln, NE. The overall project completion date is Friday, Oct. 17, 2025

 

Featured Project Information:
Find more information about this project on the SDDOT website at https://dot.sd.gov/skunkcreek.

 

Sign Up for Text Notifications:
For updates on major traffic changes, subscribe to a free text-in service. To subscribe, simply text I29BRIDGES to 605-566-4041.

 

About SDDOT:
The mission of the South Dakota Department of Transportation is to provide a safe and efficient public transportation system.


For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, please visit
https://sd511.org or dial 511.

Read more about the innovative work of the SDDOT at
https://dot.sd.gov.

 

-30-