Construction work to begin near Elmore in Spearfish Canyon
Elmore, SD – The South Dakota Department of Transportation (SDDOT) will begin grading US 14A, Spearfish Canyon, near Elmore on Monday, May 15. The project will straighten several sharp curves, approximately ½ mile north of Elmore.
Traffic will be directed through the work area by flaggers and pilot cars during working hours. Travelers can expect up to 15 minute delays. Two-way traffic will be maintained on either dirt or gravel surfacing at night.
The grading is expected to take about a month and a half. Crews will start surfacing work around the beginning of July. The entire project is scheduled to be complete on or before July 15, 2006.
For more information contact Steve Palmer with the Department of Transportation at 394-2248.
-- 30 --