Construction Work to Begin on 10th Street and Cliff Ave.
SIOUX FALLS -- Construction crews will begin work on the intersection of 10th Street (SD 42) and Cliff Ave. on Wednesday April 20th.
The project includes removing and replacing concrete in each of the five lanes on 10t Street. During construction, 10th Street traffic will be reduced to one lane in each direction. Drivers are asked to be careful when traveling through the work zone.
Dakota Contracting Corp. of Sioux Falls is the contractor on the $15,000 project. Work is scheduled to be complete by Wednesday, May 4th.
Contact Craig Smith, Sioux Falls Area Engineer at (605) 367-5680 for more information on the project.